Notice on printing and distributing the Interim Measures for evaluation of "Jiudu Cup" award of Yibin construction project (municipal high quality project)
Source: Release date: August 29, 2017 Issued by:

              

Yibin housing and Urban Rural Development Bureau

On printing and Distributing "Jiudu Cup" award for Yibin construction project

( Municipal high quality project ) Notice on Interim Measures for evaluation

                  

                                                                Letter of housing construction two thousand and twelve two hundred and forty-seven No


Each district and county housing and Urban Rural Development Bureau, Lingang district planning and Construction Environmental Protection Bureau, all directly subordinate units, and municipal construction industry association:

Yibin construction project Wine cup prize ( High quality project ) The Interim Measures for evaluation have been two thousand and twelve year five month three It was deliberated and approved by the fifth bureau director's office meeting on June, and is hereby promulgated for implementation.

 

two O May 31, 2012

 

 

 

 

Key words: urban and rural construction   engineering   Jiudu cup   Awards   way   notice

Office of Yibin housing and Urban Rural Development Bureau

two thousand and twelve year five month thirty-one day print


enclosure:



"Jiudu Cup" award of Yibin construction project

( Municipal high quality project ) Interim Measures for evaluation

Chapter one   General

Article 1 In order to implement the "construction law of the people's Republic of China" and "Regulations on the quality management of construction projects" and improve the quality level of construction projects in our city, according to the opinions of the municipal government on further accelerating the development of the construction industry (yff [2012] No. 14), the Municipal Bureau of housing, urban and rural construction of Yibin City decided to carry out the "Jiudu Cup" Municipal Quality Project Award selection in the construction industry of the city These measures are hereby formulated.

Article 2 "Jiudu Cup" is the highest honorary award for engineering quality in the construction industry of the whole city domestic Construction enterprises in Construction within the jurisdiction of Yibin City The engineering quality in the city is up to the first-class level.

Article 3 the "Jiudu Cup" award is selected once a year. The Municipal Bureau of housing and urban rural development is responsible for the specific organization and implementation of which is entrusted to the municipal construction industry association. For those who apply for "Tianfu Cup" (provincial quality structure Award), Luban Award (National Quality Engineering Award), etc comply with Wine cup Recommend the best in the award-winning projects.

Chapter two   Selection scope and conditions

Article 4   declare Jiudu cup The project shall be of the following scale:

(1) Investment one thousand and five hundred Large and medium-sized construction projects such as industry, transportation, water conservancy, electric power, etc. with a total of more than 10000 yuan;

(2) built-up area five thousand square meter Above housing projects (excluding residential buildings);

(3) The building area is in a single building three thousand Above square meters (including three thousand Square meters) of residential buildings;

(4) The building area is in twenty thousand Above square meters (including twenty thousand Square meters) of residential areas, facilities supporting, courtyard greening, etc. have begun to take shape;

(5) The project cost is one thousand Municipal infrastructure and above one thousand Professional construction and installation engineering with more than 10000 yuan five hundred Landscaping projects of 10000 yuan and above;

(6) For engineering projects without specific scale division standards, the total equivalent construction and installation workload of the declared projects shall be five hundred More than 10000 yuan.

Article 5   The declared project shall meet the following conditions at the same time:

(1) It should comply with the capital construction procedures, and all approval procedures should be complete;

(2) The engineering design is reasonable and advanced, which meets the requirements of urban planning, national and ministerial design standards and specifications;

(3) The construction is carried out in accordance with the current national construction technical standards and Specifications issued by the Ministry, and has passed the quality acceptance record of foundation and main works. The project quality is the advanced level of similar projects in the city;

(4) Unit project quality management evaluation is excellent or above;

(5) The application of new materials and new technologies is at the advanced level of the whole city.

Article 6   The following projects are not included in the scope of project selection:

(1) The project whose main structure is concealed or confidential;

(2) In the process of construction, there have been serious safety and quality accidents in the construction process, and the wages of migrant workers have been maliciously delayed, which has caused great impact on the project;

(3) Use the construction materials, components and fittings or projects with excessive chloride content in concrete that are explicitly eliminated by the state, province and city (prefecture);

Chapter three   Application procedures and information

Article 7   The application units are domestic construction general contracting enterprises and construction enterprises engaged in construction operations in Yibin City;

Article 8   Application procedure:

(1) If a construction project of a district or county is to be declared, it shall be reported to the administrative department of the construction district and county where the project is located. The administrative department of the district or county shall organize the quality and safety supervision station and other relevant departments of the district and county for preliminary examination, sign the pre evaluation opinions, and uniformly report to the Secretariat of the municipal construction industry association;

(2) The projects within the scope of eight sub district offices in the urban area shall be directly reported to the municipal construction engineering quality and safety supervision station for preliminary examination, and then submitted to the Secretariat of the municipal construction industry association;

Article 9   The application materials include:

(1) Yibin construction project Wine cup The application form is in duplicate;

(2) Text materials for introduction of project overview and construction quality( 1500-2000 Words);

(3) Construction approval documents for construction projects (construction permit, construction drawing review report and design unit's reply to construction drawing review opinions, etc.);

(4) Copies of qualification certificate of supervision unit and chief supervision engineer, and project quality evaluation report;

(5) Copies of qualification certificate of construction unit, bid winning notice, construction contract, project manager (constructor) certificate, and copies of subcontract of main subcontractors and quality inspection and evaluation data of relevant divisional and subdivisional works;

(6) Recommended form of high quality structural engineering ;

(7) Certificate of the construction unit's satisfaction with the project quality;

(8) The documents, certificates and seals provided by the application materials must be clear and easy to identify; the application materials must be accurate and true, and cover all the contents of the declared project.

The above information A4 The paper and soft cover shall be arranged into a volume and bound neatly in duplicate.

(11) Color pictures of the project (image CD) in duplicate with text description. The content of the project video CD-ROM should include: the overall picture of the project, the introduction of the quality level of the foundation pit excavation, foundation construction and structural construction in the project construction, as well as the measures reflecting the main construction methods and reflecting the new technology, new technology, new materials and new equipment, etc;

Chapter four   Project review and review

Article 10   Yibin Construction Industry Association selects experts from the association expert database to form the evaluation committee, which has a director one Deputy director two Members 6—8 The Secretariat of the municipal construction industry association is responsible for the daily work of the evaluation committee.

Article 11   The Secretariat of the municipal construction industry association shall first conduct a preliminary examination on the application materials received from each district, county or municipal unit, and those meeting the application scope and conditions shall be included in the evaluation plan. Then, 3-5 experts will be organized according to the type and quantity of the project( In principle, experts from the Committee of judges shall be responsible for this Review team, Carry out on-site review for each declared project one by one.

Article 12   The main contents of project review are as follows:

(1) Listen to the introduction of the project construction and quality by the recommended unit and the application unit, and understand the pre evaluation opinions of each district and county.

(2) Check the project quality status and listen to the user's opinions on the project quality.

(3) Refer to the internal work data of relevant projects (focusing on construction organization design, quality assurance data, project quality acceptance records, quality management activities, promotion of new technologies, new processes and new materials, qualification level of design and construction units, etc.).

(4) On site inspection of project entity quality.

Article 13   After the completion of the project review, the review team shall write a written review report, score quantitatively according to the evaluation criteria, reach a consensus, and arrange the recommended order of the reviewed projects, and submit it to the review committee.

Article 14   The evaluation shall be presided over by the chairman. The review team leader shall report the general situation of the project, the overall quality evaluation and recommendations, and answer the questions raised by the judges. After listening to the report, discussing and commenting, and then voting by secret ballot, the review project which has been approved by two-thirds or more of the members of the evaluation committee will be included in the award list.

Article 15   It will be listed in the list of awards to be awarded and publicized in the news media for public opinions and supervision. The publicity time is seven days. After publicity, the list of winners shall be submitted to the Municipal Bureau of housing and urban rural development for approval.

Chapter five   Reward and review discipline

Article 16   Get Wine cup The Municipal Bureau of housing and urban rural development shall issue trophies, certificates and circulars of commendation for the projects awarded. The project manager and chief supervision engineer will give priority to the selection of excellent constructors and engineers. When winning construction enterprises participate in the bidding of similar projects, they can add appropriate points according to the provisions of municipal government documents, and the specific bonus points shall be specified in another document.

Article 17 the reporting unit shall not engage in fraud or offer gifts. Violators will be given criticism and education according to the seriousness of the case, until the application qualification is cancelled, and the title of the awarded project shall be revoked.

Article 18   The members of the Committee and the staff of the review committee, who are honest and honest, should not accept the rewards and gifts from the experts and the reviewers. Those who violate the rules will be criticized and educated according to the seriousness of the case until they are disqualified from the assessment, and their units will be informed of the violations.

Article 19   For acquired Jiudu cup If there are major quality and safety problems or hidden dangers in the engineering quality of the award-winning project, or the project winning the prize by fraud due to the application unit providing false information, the municipal construction industry association shall organize verification and identification, and the award-winning title of the project shall be cancelled according to the procedures after verification, and shall be notified.

Chapter six   supplementary articles

Article 20   These Measures shall be implemented as of the date of promulgation.

Article 21   The Construction Industry Association of Yibin City is responsible for the interpretation of these measures.

Member style MEMBER WONDERFUL >>More

Copyright reserved: Yibin Construction Industry Association